Technical due diligence for solar plants in Chile
Independent technical due diligence before buying or financing a solar plant or PMGD in Chile: permits, P50/P90 yield, build quality and contracts.
Guide
A PMGD (pequeño medio de generación distribuida) is a power plant of up to 9 MW connected to a distribution grid in Chile. Most are solar. Investors like them for their dedicated connection procedure and the option of a stabilized price. Before buying or financing one, technical due diligence reviews seven areas: connection, permits, energy yield, design, construction, contracts and operation.
Key points
PMGD stands for pequeño medio de generación distribuida: a small distributed generator whose surplus power is up to 9 MW and which connects to the facilities of a distribution company. The rules are in Supreme Decree 88 of the Ministry of Energy, published on 8 October 2020, which replaced Supreme Decree 244.
Two features explain investor interest:
Which regime applies to the plant you are looking at is one of the first questions of any due diligence.
Status of the connection process with the distribution company, the connection criteria report, additional works required and who pays for them, feeder capacity and the risk of injection limits.
An independent assessment of expected output with P50 and P90 scenarios. P50 is the value expected to be exceeded in half of the years; P90, in nine out of ten. Lenders look at P90. The review checks the irradiation source, loss assumptions, degradation and whether curtailment was considered.
Modules, inverters, trackers and transformers: manufacturer, certifications, warranties in force and whether they transfer to the buyer.
Site inspection of mounting, cabling, earthing, drainage, fencing and roads. In an operating plant, infrared thermography and I-V curves on a sample of strings.
Construction (EPC): warranties, punch list, penalties and retentions. Operation and maintenance: scope, guaranteed availability and price. Manufacturer warranties and insurance.
In an operating plant, real data rules: output, performance ratio, availability and fault history. Two risks belong to the system rather than the plant:
The technical advisor provides the yield and curtailment assumptions; the financial model belongs to the financial advisor. That is why technical, legal and financial due diligence are coordinated.
| Area | Documents |
|---|---|
| Connection | Connection request and criteria report, connection agreement, correspondence with the distribution company |
| Environmental | Environmental approval or applicability ruling, monitoring reports |
| Land | Titles, lease, easements |
| Engineering | As-built drawings, design calculations, yield study |
| Equipment | Datasheets, certificates, warranties, test reports |
| Construction | EPC contract, acceptance certificates, punch list |
| Operation | O&M contract, monitoring data, monthly reports, fault log |
Three to six weeks, depending on the size of the asset and how organized the data room is. Carlos Jofré publishes his fee: from UF 240 for a PMGD up to 9 MW. The report can be delivered in English. See the technical due diligence service.
FAQ
It stands for pequeño medio de generación distribuida, a small distributed generator: a plant with up to 9 MW of surplus power connected to a distribution grid in Chile. Most are solar.
If it exceeds 3 MW, yes: power plants above 3 MW must enter Chile's environmental impact assessment system.
It is a mechanism that lets a PMGD owner sell energy at a regulated, stabilized price instead of the hourly marginal cost. The National Energy Commission (CNE) calculates it. Decree 88 changed its methodology in 2020, with a transitional regime for earlier projects.
In 2025, 6,084 GWh of renewable energy were curtailed, according to the renewable energy association ACERA. Without curtailment, non-conventional renewables would have supplied about 49.4% of the energy instead of 42.4%.
Sources
Keep reading
Independent technical services
Independent technical due diligence before buying or financing a solar plant or PMGD in Chile: permits, P50/P90 yield, build quality and contracts.
Independent technical services
Independent audit of solar plants in Chile: performance ratio, infrared thermography, I-V curves and a loss report ranked by financial impact.
Track record
Carlos Jofré is a Chilean solar engineer: co-founder of Ecoenergías (2011), founder of SolarPro (2017) and the mind behind 17 CORFO-funded R&D projects.
from UF 90. The first 15-minute call is free of charge.